View all news articles linked to 100% Wolf – The family roller coaster at Plopsaland Deutschland.
100% Wolf Train Stalls with Guests on Board
A 100% Wolf train stalled halfway through the layout, just before the wolf head, and guests were evacuated. Plopsa said the issue was caused by a combination of higher temperatures and heavier loading.
More context
In early May 2026, 100% Wolf faced another highly visible incident. A train stopped halfway through the layout, just before the large wolf head, because according to Plopsa it did not have enough speed to reach the endpoint. Guests were on board and had to be evacuated by staff. They received a drink and a pass to skip another queue as compensation. The coaster completed test runs afterwards and was expected to reopen the next day. A spokesperson said there was no major underlying problem: higher temperatures and a heavier load had combined to affect the train’s speed. Even so, the incident fitted into the ride’s sensitive early operating history after earlier technical disruptions.
Shortly after opening, 100% Wolf faced breakdowns, closures and limited capacity. A Gerstlauer software update was intended to solve the issues, while waits rose above ninety minutes.
More context
Less than three weeks after opening, 100% Wolf showed the difficult side of launching a complex new coaster. Looopings reported that visitors regularly found the ride closed or operating with restrictions. Low temperatures played a role, but there were also technical disruptions and several closure days around the busy Easter period. Because 100% Wolf was being promoted as the park’s new headline attraction, the unstable start stood out even more. Gerstlauer installed a software update, after which the ride reopened, but only with one train at first. That pushed waits beyond ninety minutes. For guests, the new family coaster was available again, yet not yet delivering the capacity and reliability expected from a major seasonal novelty.
100% Wolf Officially Opens at Plopsaland Deutschland
100% Wolf officially opened with a ceremony and video report. The 11-million-euro Gerstlauer coaster was presented as a bridge between children’s attractions and more intense coasters.
More context
On 22 March 2026, 100% Wolf finally received its official opening at Plopsaland Deutschland. Looopings captured the ceremony, the themed area and the ride in a detailed video report. The coaster showed why the project had drawn so much attention: two lift hills, sharp turns, a tunnel through the wolf head, a steep dead-end hill and a backwards section. During the opening, two of the three trains were operating. The purple trains, wolf front and poodle detail tied the ride visibly to the Studio 100 story. Park director Bernd Beitz described 100% Wolf as a bridge between children’s attractions and more intense coasters. After delays and anticipation, the park finally gained its new family landmark.
First Onride Footage Shows Full 100% Wolf Experience
Plopsaland Deutschland released the first onride video of 100% Wolf shortly before opening. The footage showed the lift, booster, spike, backwards section and wolf-head rockwork.
More context
Just days before opening, Plopsaland Deutschland gave fans the first full onride look at 100% Wolf. The video showed how the ride is built: a chain lift, a tyre-driven booster lift, a winding layout, a dead-end spike and then a short backwards section before the train returns forward to the station. For visitors, this was practical news because it revealed how forceful and playful the family coaster actually felt. For coaster fans, it confirmed comparisons with Wakala while also showing 100% Wolf’s own identity through the large wolf-head rockwork and Studio 100 theme. The footage arrived exactly when the long-awaited opening was finally within reach.
New images from Plopsaland Deutschland showed 100% Wolf nearly finished, with trains on the track and the wolf-shaped rockwork visible. The opening was scheduled for 22 March 2026.
More context
Two weeks before the planned opening, Plopsaland Deutschland released new photos of 100% Wolf. The ride appeared almost complete: trains were already running along the track and passing the large wolf-head rockwork. That helped remove much of the doubt left by the earlier delay. The park announced an opening date of Sunday 22 March 2026, including a ceremony between noon and 1 p.m. The photos also underlined what the coaster was meant to deliver for guests: a 760-metre family ride with a spike, a backwards section and enough theming to make the Studio 100 world visible. For fans, it was the final visual confirmation before opening day.
100% Wolf Begins Test Runs Ahead of Season Opening
Plopsaland Deutschland began test runs on 100% Wolf. The footage showed the delayed Gerstlauer family coaster being prepared for its planned 22 March 2026 opening.
More context
By late January 2026, 100% Wolf was visibly moving. Plopsaland Deutschland shared test footage of the new family coaster, now being prepared for the start of the season after missing its 2025 target. The runs confirmed several key parts of the design: 645 metres of track, a prominent spike and a ride experience extended to 760 metres by its backwards section. For fans, this was more than a technical milestone. After months of delays and construction updates, the 22 March opening suddenly looked concrete. For regular visitors, the message was just as clear: the Studio 100 coaster was no longer a future promise, but a ride that would soon join the park’s lineup.
Plopsaland Deutschland postponed 100% Wolf to spring 2026 after all. The park said it wanted to open the coaster only once the full themed experience was ready from day one.
More context
In early September 2025 the delay many fans had started to expect became official: 100% Wolf would not open in 2025. Plopsaland Deutschland had previously maintained that the coaster would become operational in autumn, followed by an official opening in 2026. That promise was withdrawn. The park’s website now stated that the family coaster would open in spring 2026, at the start of the season. The explanation was that guests should receive a complete and spectacular experience from the first day. In practice, that meant no soft opening with unfinished theming. 100% Wolf would wait until the ride, story and surrounding area could be presented as one finished package.
100% Wolf’s Giant Wolf Head Takes Shape at Plopsaland Deutschland
New construction photos showed the giant wolf head for 100% Wolf taking shape. The set piece became the ride’s visual centrepiece, with trains planned to pass through the wolf’s mouth.
More context
By August 2025 the focus had shifted from concept art to visible construction. Fan photos showed the large rockwork wolf head already well advanced. That structure was set to become the signature image of 100% Wolf: trains would pass through the animal’s mouth, making the theme part of the physical ride experience rather than just a name. The track was already standing and the station building was also taking shape. For visitors and coaster fans, the photos made the project feel real after months of plans, specifications and timeline questions. They also confirmed that Plopsaland Deutschland wanted to present the family coaster as a fully themed Studio 100 experience.
Plopsa Addresses Doubts About 100% Wolf Opening Year
When construction fencing referred to 2026, Plopsa stressed that 100% Wolf was still expected to be ready in 2025. The park said 2026 referred to the official opening and completed theming.
More context
In September 2024 confusion grew around the timeline for 100% Wolf. Construction fencing at Holiday Park Germany referred to a new family coaster in 2026, even though the project had previously been linked to 2025. Plopsa tried to calm those doubts: according to a spokesperson, the coaster would be ready in 2025, while the official opening was planned for 2026. That created a distinction between technical completion and a fully themed guest experience. For fans, the message mattered because 100% Wolf was part of a broader investment push in the German park. It later became an important marker once the schedule did shift after all.
During a fan day, Gerstlauer revealed the technical details of 100% Wolf. The family coaster would stand 17.5 metres tall, use 645 metres of track and offer a 760-metre ride thanks to its backwards section.
More context
One month after the first concept art, 100% Wolf became much more concrete. During a dedicated fan day, Gerstlauer presented the specifications for the new family coaster at Plopsaland Deutschland. The ride would be 17.5 metres high and use 645 metres of track, while the backwards section would give guests a total ride distance of 760 metres. Its top speed was set at 55 kilometres per hour. Capacity was also defined: three trains with twenty seats each, theoretically moving around one thousand guests per hour. Element names such as twisted stall and double twisted camelback showed that Plopsa was aiming for an active family coaster rather than a simple themed ride.
Plopsa presented the first design for 100% Wolf, a Gerstlauer family coaster planned for Holiday Park with a werewolf theme. The ride was positioned as a bridge between children’s coasters and larger thrill rides.
More context
In May 2024 Plopsa gave the first clear look at the family coaster planned for Holiday Park. The ride would use the Studio 100 film 100% Wolf as its theme and represented an investment of 11 million euros. The layout immediately stood out to coaster fans: a Gerstlauer design with a regular lift, a second powered lift, a dead-end section and part of the ride taken backwards. That placed the coaster between the park’s small indoor ride and its more intense thrill coasters. Its location between Sky Scream and the lake also showed that 100% Wolf was meant to become a visible new landmark rather than a minor children’s addition.